Status report on transformational and major Crown projects

Canadian High Arctic Research Station

Description: In the 2007 Speech from the Throne, the Government of Canada emphasized that there are both new opportunities and new challenges in the North, and indicated it would bring forward an integrated Northern Strategy focused on strengthening Canada's sovereignty, protecting environmental heritage, promoting economic and social development, and improving and devolving governance. The Government also promised to "build a world-class Arctic research station that will be on the cutting edge of Arctic issues, including environmental science and resource development. This station will be built by Canadians, in Canada's Arctic, and it will be there to serve the world." In August 2010, it was announced that Cambridge Bay, Nunavut, would be the location for the Canadian High Arctic Research Station (CHARS) campus.

Architectural design, construction, equipment, and furniture for CHARS campus, as well as the implementation of the science and technology program are estimated at a value of approximately $250 million up to and including 2017–18. Crown-Indigenous Relations and Northern Affairs Canada (CIRNAC) is responsible for delivering on the architectural design, construction, equipment, and furniture for the campus at an estimated total cost of $204.8 million. The remaining $46.2 million for implementation of the science and technology program was initially administered by Indigenous and Northern Affairs Canada and is now administered by Polar Knowledge Canada.

The CHARS campus, now largely operational, is bringing an enhanced level of research and analysis to Canada's North.

Project outcomes:

Industrial benefits:

Sponsoring department: Crown-Indigenous Relations and Northern Affairs Canada

Contracting authority: Public Services and Procurement Canada

Participating departments: Not applicable

Prime contractor: The construction contractor is the EllisDon Corporation (Ottawa, Ontario, Canada) in joint venture with NCC Dowland Ltd. (Whitehorse, Yukon, Canada).

Major subcontractors: Subcontracting is managed by the EllisDon Corporation (Ottawa, Ontario, Canada).

Project phase: Implementation
Major milestones Date
Creation of CHARS announced Speech from the Throne 2007
CHARS feasibility: $2 million over 2 years Budget 2009
CHARS design: $18 million over 4 years Budget 2010
Cambridge Bay location announced by Prime Minister August 2010
CHARS mandate announced by Minister December 2010
Feasibility study September 2011
Request for proposal (RFP) for design consultant tendered September 2011
RFP for design consultant closed November 2011
Design consultant contract announced August 2012
RFP for construction management services tendered November 2012
RFP for construction management services closed December 2012
Site announced in Cambridge Bay February 2013
Construction management contract for advisory services awarded June 2013
Construction management contract for constructor services awarded May 2014
Begin site preparation June 2014
Begin construction August 2014
Complete design development January 2015
Complete land acquisition in Cambridge Bay March 2015
Complete Triplex Accommodation Buildings November 2015
Complete Field and Maintenance Building March 2017
Partial Substantial Completion of Main Research Building July 2018
Authority to Operate from Shared Services Canada October 2018
Performance Inspections Fall 2018
Completion of Deficiency Review Process Winter 2018/2019
Substantial Completion of the Main Research Building *March 2019
Commissioning and Civil Works *Spring/Summer 2019
Certificate for Completion of Construction *October 2019
*Anticipated milestones

Progress report and explanation of variances: Performance inspections, including those for the mechanical and electrical systems of the Main Research Building occurred in the fourth quarter of 2017–18. In June 2018, partial substantial performance was granted and access was allowed to the Main Research Building. The final phase of construction is focused on outstanding items, including aspects of the mechanical systems and civil works (i.e. outside road and landscaping).

Legislative authorities to transfer the administration of the federal real property from CIRNAC to the CHARS corporation are being sought by Order in Council.

The certificate for Completion of CHARS construction is expected in October 2019.

Did you find what you were looking for?

What was wrong?

You will not receive a reply. Don't include personal information (telephone, email, SIN, financial, medical, or work details).
Maximum 300 characters

Thank you for your feedback

Date modified: