Archived - Status Report on Projects Operating with Specific Treasury Board Approval
Archived information
This Web page has been archived on the Web. Archived information is provided for reference, research or record keeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.
Project Name and Project Phase | Original Estimated Total Cost (dollars) | Revised Estimated Total Cost (dollars) | Actual Total Cost (dollars) | 2015–2016 Main Estimates (dollars) | 2015–2016 Planned Spending (dollars) | 2015–2016 Total Authorities (dollars)a | 2015–2016 Actual Spending (dollars) | Expected Date of Close-Out |
---|---|---|---|---|---|---|---|---|
Link to the organization's program: The North — 4.3 Northern Land, Resources and Environmental Managementb | ||||||||
Giant Mine | 1,179,305,914 | 1,227,687,834 | 335,721,328 | 24,552,777 | 54,059,696 | 44,178,297 | 56,241,994 | 2028–2029 |
Tundra Mine | 8,527,388 | 273,838 | 6,101,289 | 6,090,868 | 8,527,333 | 2018–2019 | ||
United Keno Hills Mines | 48,879,325 | 5,461,479 | 6,217,898 | 10,055,930 | 4,595,803 | 2023–2024 | ||
Bullmoose and Ruth Mines | 4,502,434 | 6,723,885 | 500,000 | 8,498,200 | 484,739 | 2022–2023 | ||
FOX-E — Durban Island Mines | 12,065,436 | 0 | 3,213,535 | 165,600 | 3,428,889 | 2015–2016 | ||
Great Bear Lake Mines | 21,233,596 | 7,002,485 | 694,259 | 21,761,377 | 1,196,160 | 2026–2027 | ||
Link to the organization's program: The North — 4.2: Northern Science and Technology | ||||||||
Canadian High Arctic Research Station (CHARS)c | 145,524,772 | 195,537,456 | 102,071,447 | 43,626,194 | 44,995,969 | 49,746,921 | 57,209,028 | 2018–2019 |
a In this table, the column "Total Authorities" reflects only the annual Planned Spending for fiscal year 2015–2016 as outlined in the Original Estimated Total Cost or Revised Estimated Total Cost columns. b Main Estimates for Northern Contaminated Sites Program under Northern Land, Resources and Environmental Management are based on the amounts by site in the Treasury Board submission. Planned Spending amounts were determined from the approved Detailed Work Plans. c The project scope was re-defined and the total project cost was amended to $145.5 million in May 2014, with an increase of $50 million in 2015. Actuals are higher than Authorities as some activities ($5.4 million) have been postponed from 2014–2015 to 2015–2016, and were not included in the 2015–2016 Total Authorities. Moreover, $1.4 million was expended for the Science and Technology Program, and is not included in Total Authorities. Note that 2015–2016 Planned Spending corresponds to 4.2.2 (Science initiatives) and includes administration cost to support the Northern Science and Technology program. The CHARS project excludes INAC internal services costs (except for Authorities). Please note the following:
|