Changes to the Nunavut Waters and Nunavut Surface Rights Tribunal Act (NWNSRTA)
The Yukon and Nunavut Regulatory Improvement Act (YNRIA) includes improvements to the regulatory regimes governing resource development in Yukon and Nunavut. These changes involved amendments to two existing pieces of legislation: the Nunavut Waters and Nunavut Surface Rights Tribunal Act (NWNSRTA) and the Yukon Environmental and Socio-economic Assessment Act (YESAA).
A number of the changes to the NWNSRTA (administrative monetary penalties, security arrangements and fines) came into force on June 18, 2015, when the YNRIA received Royal Assent, and became law.
The remaining changes to NWNSRTA (time limits, life of project water licences and cost recovery) will come into force within the next 12 months. This will allow those affected by the change to prepare appropriately, and allow time for consultation on the development of regulations linked to the amendments.
Highlights of Changes to NWNSRTA
Before Bill S-6 | New Features |
---|---|
Time Limits (Not yet in force) | |
|
|
"Life of Project" Water Licenses (Not yet in force) | |
|
|
Cost Recovery (Not yet in force) | |
|
|
Administrative Monetary Penalties (AMPs) (In force now) | |
|
|
Fines (In force now) | |
|
|
Posting Security/'Over Bonding' (In force now) | |
|
|