Comprehensive Audit of the AANDC and Attawapiskat First Nation Management Control Framework - Follow-up Report Status Update as of March 31, 2014

PDF Version (27 Kb, 3 Pages)

Action Plan Implementation Status Update Report to the Audit Committee - As of March 31, 2014

Regional Operations

Comprehensive Audit of the AANDC and Attawapiskat First Nation Management Control Framework
Approval Date: 09/28/2012

Project Recommendations Action Plan Expected
Completion Date
Program Response
1. The Ministerial Loan Guarantee process should be reviewed, in consultation with CMHC, giving consideration to the following:
  • Developing stricter enforcement practices with respect to eligibility requirements and taking remedial action with regard to non-compliance;
  • Implementing practices to certify completion of housing units by a suitably qualified professional according to National Building Code of Canada standards or an accepted equivalent set of standards;
  • Conducting a risk-based periodic review of First Nation inspection records; and,
  • Developing formal practices (e.g. Memorandum of Understanding between AANDC and CMHC) to require that the results of CMHC Physical Condition Reviews and client visit reports be shared with AANDC as a mandatory requirement of the eligibility process.
We concur with this recommendation.

Lenders providing loans backed by Ministerial Loan Guarantees (MLGs), including CMHC, must assure due diligence with loan management, including prudent lending practices, arrears, default and reporting to AANDC. AANDC will work with lenders to identify opportunities for improving due diligence processes.

AANDC is exploring mechanisms for improving National Building Code compliance.
Q3, 2013-14 Status: Underway

Update/Rationale:
As of 31/03/2014:

AANDC and CMHC have established a data sharing mechanism, pursuant the April 2013 MOU entered into by the parties. AANDC has been provided secure access to CMHC’s Client Visit Reports and Physical Condition Review reports.

Revised expected completion date: Q1 2014-15

AANDC and CMHC have established a process for regular monthly meetings at the DG/VP level to discuss issues of concern and ensure co-ordination of housing activities.

AANDC is in the process of revising the Terms and Conditions for Ministerial Loan Guarantees in order to update them in general, and reflect the changes that will be coming with the new Environment Review Process.

Revised expected completion date: Q4 2014-15

AES: Implementation ongoing.

2. The Capital Facilities and Maintenance (CFM) Program terms and conditions should be reviewed, giving consideration to the following:
  • Including eligibility requirements which require demonstrated financial management capability with respect to the First Nation's housing program (e.g. Replacement Reserve Account, collection practices, reliable housing reports);
  • Adding the requirement that a separate Housing Authority be established as a CFM eligibility requirement;
  • Discontinuing the practice of allowing minor core capital to be used for the purposes of debt repayment; and,
  • Clarifying housing report definitions and developing housing performance indicators which can be used to assess maintenance needs and establish a baseline on which to measure ongoing performance.
We concur with this recommendation.

AANDC will review the CFM Program as it relates to housing, and consider the issues identified by this audit when next renewing the Terms and Conditions for the program.
Q3, 2013-14 Status: Underway

Update/Rationale:
As of 31/03/2014:

A concept/framework for the reform of management of minor capital funding (of which housing is a part) was developed in Q4. In 2014-15, First Nations will be required to indicate where they plan on investing all formula-based funding in their 2015-16 community First Nation Infrastructure Investment Plan to demonstrate accountability for its use. A risk-based approach will be used in evaluating and approving these plans. Tools and guidance documents are now starting development. The department is examining the impact of this minor capital funding reform on housing allocations to First Nations.

A revised Performance Measurement Strategy for the CFMP will be presented to the Evaluation, Performance Measurement and Review Committee on April 25, 2014. An analysis of housing targets and performance indicators will be explored during the implementation of this strategy. This analysis is expected to be completed by the first quarter of fiscal year 2014-15.

Revised Expected Completion date: Q1 2014-15

AES: Implementation ongoing.
 
 

Did you find what you were looking for?

What was wrong?

You will not receive a reply. Don't include personal information (telephone, email, SIN, financial, medical, or work details).
Maximum 300 characters

Thank you for your feedback

Date modified: