Audit of On-Reserve Housing - Follow-up Report Status Update as of March 31, 2013
PDF Version (34 Kb, 6 Pages)
Action Plan Implementation Status Update Report to the Audit Committee - As of March 31, 2013
Regional Operations
Audit of On-Reserve Housing (09090)
Approval Date: 24/09/10
Project Recommendations |
Action Plan | Expected Completion Date |
Program Response |
---|---|---|---|
1. The Assistant Deputy Minister, Education and Social Development Programs and Partnerships Sector should assess and determine the most appropriate means to fund on-reserve housing. |
|
Complete | A) Status: no change in status Update/Rationale: As of 30/09/2011: No change is required to the current housing funding structure. B) Status: completed, request to close. Update/Rationale: As of 30/09/2011: AANDC's Capital and Facilities and Maintenance Program, of which housing funding is a part, has been assessed for compliance with the new Policy on Transfer Payments. First Nations recipients have been assessed for capacity and risk using the General Assessment, and funding relationships have been tailored to the results. AES: Closed – Fully Implemented |
|
Q4, 2011-12 | ||
2. The Assistant Deputy Minister, Education and Social Development Programs and Partnerships Sector should identify and implement a methodology for allocating housing funds that reflects housing needs at both the regional and First Nation community level. |
|
Q3, 2011-12 | Status: Completed, request to close. Update / Rationale: As of 31/12/2012: A Management Control Framework has been established for the CFM Program to ensure that the National Capital Planning process, roles and responsibilities for regions and HQ, and risk-based approvals and management approaches are established for the delivery of CFM Program funding. Status: Completed, request to close. Update / Rationale: As of 31/03/2013: Completed, request to close as per the December 2012 update. Status: On-going Update / Rationale: As of 31/12/2012: A new approach to the management and control of minor capital and O+M funding will be piloted in the Ontario Region in 2013-14. A management control framework for the pilot is being developed and will be ready by April 1, 2013. The results of this pilot project will be used to inform the implementation of this new approach nationally, beginning in 2014-15. The Management Control Framework will be updated at that time to include the minor capital and O+M funding streams. Status: On-going Update / Rationale: As of 31/03/2013: A new approach to the management and control of minor capital and O+M funding will be piloted in the Ontario Region in 2013-14. A management control framework for the pilot is being developed and will be ready by April 1, 2013. The results of this pilot project will be used to inform the implementation of this new approach nationally, beginning in 2014-15. The Management Control Framework will be updated at that time to include the minor capital and O+M funding streams. AES: Implementation on-going. Recommendation will be closed once Management Control Framework has been updated to include minor capital and O&M. |
|
Q3, 2011-12 | ||
3. The Assistant Deputy Minister, Education and Social Development Programs and Partnerships Sector, in collaboration with the Senior Assistant Deputy Minister, Regional Operations Sector, should conduct a review of the performance indicators and related information to be collected for on-reserve housing to ensure that they are aligned with the department’s housing program design, and that they can demonstrate achievement of expected outcomes. |
|
Q1, 2011-12 | Status: Completed Update/Rationale: As of 31/03/2011: AES: Closed |
4. The Assistant Deputy Minister, Education and Social Development Programs and Partnerships Sector, in collaboration with the Senior Assistant Deputy Minister, Regional Operations Sector, should develop and implement a risk management framework specific to on-reserve housing, including a formal monitoring or compliance audit / housing inspections process. |
|
Q2, 2011-12 | A) Status: close Update/Rationale: As of 31/03/2012 request to close as per September 30/11 update. B) Status: on-going, expected completion date Q1, 2012-2013. Update/Rationale: As of 31/03/2012: Performance indicators to be reported on in 2015. Self reported "adequate housing" is completed; housing sub-text of community well-being index is dependent on Statistics Canada Census data; and Valid Housing Plan is awaiting regional input on content in order to develop a finalized definition. Ongoing Regional and community oversight visits are being conducted to assess the management of the CFMP. C) Status: close Update/Rationale: As of 31/03/2012: requested to close as per September 30, 2011 update. AES: Closed. |
|
Q2, 2011-12 | ||
|
Complete | ||
5. The Assistant Deputy Minister, Education and Social Development Programs and Partnerships Sector should ensure that comprehensive national guidelines for the management of the housing component of the CFM Program are developed and disseminated. |
|
Q2, 2011-12 | Status: on-going, expected completion date Q2, 2012-13. Update/Rationale: As of 31/03/2012: AANDC has compiled detailed Roles and Responsibilities. Assembly of First Nations to convene a meeting of the working group to develop a joint summary document on the roles and responsibilities of key housing players. Toolkit completed and disseminated. Status on-going, expected completion date Q4, 2012-13. Update / Rationale: As of 30/09/2012: The Assembly of First Nations led working group met in August, 2012 to review draft documentation on Roles and Responsibilities of key stakeholders, including the AFN, CMHC, HC and AANDC. The National First Nations Housing Liaison Committee will meet later this fiscal year to finalize documentation and develop the dissemination strategy. Status: Closed Update/Rationale: As of 31/03/2012: as per September 30/12 update, this is recommended to be closed. AES: Closed- Substantially implemented. |
6. The Senior Assistant Deputy Minister, Regional Operations Sector, in collaboration with the Assistant Deputy Minister, Education and Social Development Programs and Partnerships Sector, should ensure that the risk that First Nations’ housing does not transfer to individual homeowners as required for Market Based Housing projects, is appropriately managed. |
|
Q3, 2010-11 | Status: Completed Update/Rationale: As of 31/03/2011: Monitoring conducted but no Regions have identified need for a risk management plan. AES: Closed |
|
Q4, 2010-11 | ||
|
Q3, 2010-11 | ||
7. The Assistant Deputy Minister, Education and Social Development Programs and Partnerships Sector, in collaboration with the Senior Assistant Deputy Minister, Regional Operations Sector, should ensure that the development of project assessment and funding decision methodologies reflects regional requirements in the design of future programs/initiatives similar to housing funded by CEAP. |
|
Q4, 2010-11 | Status: Completed Update/Rationale: As of 31/03/2011: New MCF to be provided to Ops Committee scheduled for, April 2011. AES: Closed |
|
Q4, 2010-11 |