Archived - Audit of Capital Facilities and Maintenance - Follow-up Report Status Update as of March 31, 2010

Archived information

This Web page has been archived on the Web. Archived information is provided for reference, research or record keeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.

PDF Version (55 Kb, 11 Pages)

 

 

Action Plan Implementation Status Update Report To The Audit Committee - As of March 31, 2010

Education and Social Development Programs and Partnerships - Community Infrastructure

Audit of Capital Facilities and Maintenance (200719)
AEC Approval Date: 04/12/2008

Project Recommendations Action Plan Expected Completion Date Program Response
1. The Director General, Community Infrastructure Branch should work closely with the Director General, Operations and Planning Support Branch and the Chief Financial Officer to reassess the funding authorities and First Nation funding agreements that currently provide flexibility in the funding on minor capital and operations & maintenance expenditures, giving consideration to providing funding on a more 'targeted' basis. a) Chief Financial Office to develop standardized departmental approach to drafting First Nation funding agreements that respond to funding authority requirements under the new TB Transfer Payment Policy. 30/09/2009 Status: Pending Implementation

Update/Rationale:
As of 31/03/2010:

a. Ongoing- CFO has until March 31, 2011 to develop a departmental action plan in response to the new Transfer Payment Policy. CFO currently has in place a national standardized approach relating to funding agreements, which will be updated to respond to requirements under the new policy and directive on transfer payments.

b) Community Infrastructure Branch to work with Chief Financial Office (Transfer Payments and Financial Policy Directorate) to understand broad framework of new Treasury Board Transfer Payment Policy and how it affects future funding authorities /agreements as it relates to community infrastructure and apply these principles to the future funding agreements. 31/12/2009 b. Ongoing- Community Infrastructure Branch continues to work with CFO to understand how the new Transfer Payment Policy will affect future funding agreements as they relate to community infrastructure.
c) Operations and Planning Support Branch to work with Regional Offices (Chief Financial Office and Community Infrastructure Branch in support) to develop mechanisms to bring about more effective oversight of minor capital and operations & maintenance spending in First Nation funding agreements. This work will be aligned with a and b. 31/03/2010 c. Ongoing- Once a) and b) are complete, OPS Branch will work with regional offices to implement new funding agreements and authorities associated with the new Transfer Payment Policy. Pending completion of the above work, OPS Branch is working with CIB and CFO staff to assist in the development of mechanisms, which will improve oversight of minor capital and operations and maintenance spending in First Nations funding agreements. This work will be aligned with the Quality Management Program.

AES: No comment at this time

2. The Director General, Community Infrastructure Branch and the Director General, Operations and Planning Support Branch should ensure that the roles and responsibilities for performance management at the senior management and board / committee level are defined and communicated, and that performance information, including Key Performance Indicators, is incorporated into ongoing performance management at both the national and regional levels. a) Community Infrastructure Branch to develop a CFM Program-specific Performance Measurement Strategy (replacement for now defunct RMAF/RBAF) in conjunction with program renewal. Performance Measurement Strategy will spell out roles and responsibilities, as well as key performance indicators. Key performance indicators will also continue to be reported on quarterly through the department's smart reporting process. 31/12/2009 Status: Pending Implementation

Update/Rationale:
As of 31/03/2010:

a. Completed - Performance Measurement Strategy and Risk Profile were approved by the Department's Evaluation, Performance Measurement and Review Committee in September 2009.

b) Community Infrastructure Branch to work with Operations and Planning Support Branch to restructure terms of reference for the National Capital Management Board and/or other senior management committees, clarify roles and responsibilities with respect to CFM Program, and establish key performance measurement indicators for ADM-Committee level (i.e., review of quarterly reporting input, follow up on A&E action plans, DPR/RPP input, etc.). 30/06/2009 b. Completed - The National Capital Management Board has been dissolved. The work of the Board has been taken over by Operations Committee. To reflect these new roles and responsibilities, new terms of reference for the Committee have been approved.
c) Operations and Planning Support Branch to communicate roles and responsibilities to Regional Offices and develop procedures to collective performance information on key performance indicators and ensure that the key performance indicators are incorporated into regional and national level Performance Management Agreements. 31/03/2010 c. Ongoing - OPSB is working with CIB to implement the Performance Measurement Strategy and Risk profile and ensure that key performance indicators are incorporated into all relevant reporting and performance management agreements. An update on the progress of implementation will be presented to the Department's Evaluation, Performance Measurement and Review Committee at their upcoming meeting in May 2010.

AES: No comment at this time.

3. The Director General, Community Infrastructure Branch and the Director General, Operations and Planning Support Branch should develop, formalize, document and implement a risk management framework specific to the CFM Program that incorporates roles and responsibilities at the Headquarters and regional senior management and board / committee level and an appropriate level of oversight / monitoring / quality assurance role for Headquarters over regional practices. a) Community Infrastructure Branch to develop a CFM Program-specific Performance Measurement Strategy in conjunction with program renewal. The Strategy will include a risk management framework that details oversight and quality assurance functions for Headquarters and regions. 31/12/2009 Status: Pending Implementation

Update/Rationale:
As of 31/03/2010:

a. Completed - Performance Measurement Strategy and Risk Profile were approved by the Department's Evaluation, Performance Measurement and Review Committee in September 2009.

b) Operations and Planning Support Branch to work with Regional Offices to implement risk management framework and oversight and quality assurance functions for Headquarters and regions 31/03/2010 b. Ongoing - OPSB is working with CIB and regional offices to implement the Performance Measurement Strategy and Risk profile and ensure that key performance indicators are incorporated into all relevant reporting and performance management agreements. An update on the progress of implementation will be presented to the Department's Evaluation, Performance Measurement and Review Committee at their upcoming meeting in May 2010. The CFM Program Management Control Framework, which helps identify key program risks and mitigate them, has been implemented. OPSB is also developing new Quality Management Program to ensure the quality of the CFM Program is maintained and improved upon. CIB is also contributing to the development of a General Assessment to assess recipient and program risk led by OPSB.

AES: No comment at this time.

4. The Director General, Community Infrastructure Branch and the Director General, Operations and Planning Support Branch should conduct a review of the methodology and process for allocating CFM Program funding from Headquarters to regions. a) Community Infrastructure Branch to work with Chief Financial Office, Operations and Planning Support Branch and Regional Offices to explore options for enhancing the methodology and process for allocating CFM Program funding (core and non-core) from Headquarters to regions. 31/12/2010 Status: Pending Impending

Update/Rationale:
As of 31/03/2010:

a. Ongoing - CIB is working with CFO on options for the allocations of CFM Program funding from HQ to regions. Work has commenced on assessing how minor capital funding should be distributed to regions and First Nations communities. Also, a new Schools Priority Ranking Framework has been developed in association with a National Allocation Methodology for First Nations Education Facilities that were approved by INAC's Operations Committee on April 20th, 2010.

b) Community Infrastructure Branch to work with Chief Financial Office, Operations and Planning Support Branch and Regional Offices to take results from 4.1.1 and apply to each of the asset classes (i.e., water, schools, housing). The current engineering assessment for water will also provide information for this exercise. 31/12/2011 b. Ongoing - CIB is working with CFO on options for the allocations of CFM Program funding from HQ to Regions. Research is taking place to develop options for allocations from HQ to Regions. A working group is being created with Regions to discuss options for reforming minor capital allocations. Determining optimal allocations in other areas such as operations and maintenance funding is also being considered.

AES: No comment at this time

5. The Director General, Community Infrastructure Branch and the Director General, Operations and Planning Support Branch should ensure that updated and comprehensive national guidelines for the management of the CFM Program are developed and disseminated to program management in the regions. a) Community Infrastructure Branch to develop/update high level flowchart, indicating various activities undertaken by the department and the purpose of each activity. Will cover generic processes (major capital, minor capital, etc.) and theme-specific processes (water major capital, school major capital, etc.) 30/06/2009 Status: Pending Implementation

Update/Rationale:
As of 31/03/2010:

a. Ongoing - A Procedures Manual is being developed to provide comprehensive national guidelines for the management of the CFM Program. A number of procedures have been completed as chapters and have been implemented in the regions. Specifically, procedures for capital planning through First Nations Infrastructure Investment Plans, Major Capital projects, and the Circuit Rider Training Program have been drafted and implemented. The development of further procedures (such as minor capital) is ongoing. Additionally, a logic model for the CFM Program was developed in the Performance Measurement Strategy to assist program guidance by providing clear program linkages between key program activities and ultimate program outcomes.

b) Operations and Planning Support Branch to work with regions to implement work done in a). 30/09/2009 b. Ongoing - OPSB is working with CIB to implement procedures as they are developed.
c) Community Infrastructure Branch to develop/update 2nd tier guidelines that will detail roles and responsibilities, the management control framework for the CFM Program, and authorities to approve funding expenditures. Flowcharts in 5.1.1 will also be expanded to additional themes including roads and bridges major capital and electrification major capital. 30/09/2009 c. Completed - A Management Control Framework has been developed for the CFM Program to improve program management. Detailed program procedures for capital planning have been developed and implemented.
d) Operations and Planning Support Branch to work with regions to implement work done in 5.1.3. 30/09/2009 d. Ongoing - OPSB is implementing procedures as they are developed.
e) Community Infrastructure Branch to compile/consolidate national standards for engineering and/or construction standards, templates, financial coding, detailed audit and compliance regimes, checklists for business processes, etc. Regional variations may be introduced to account for different regional factors. Identified gaps in information will be filled with new procedures/processes development as required. 31/12/2009 e. Ongoing - CIB has collected relevant documents being used by regions to manage the CFM Program. A process of conference calls with regions was undertaken to discuss best practices. This review has helped create procedures for capital planning through First Nations Infrastructure Investment Plans, Major Capital projects, and the Circuit Rider Training Program. Input from regions will continue in the development of further procedures. For example, a working group on minor capital will be established to develop national procedures for minor capital in Q1 2010.
f) Operations and Planning Support Branch to work with regions to implement work done in 5.1.5. 31/12/2009 f. Ongoing - OPSB is working with regional offices to implement procedures as they are developed.

AES: Past expected completion dates.

6 a) The Director General, Community Infrastructure Branch should develop and communicate guidelines for the categorization of projects to be managed as major capital projects. a) Community Infrastructure Branch to draft/update comprehensive national guidelines for the categorization of projects to be managed as major capital projects. 30/06/2009 Status: Completed

Update/Rationale:
As of 31/03/2010:

6. a) Ongoing - A Management Control Framework and procedures for Major Capital projects have been developed and implemented. The definition of Major Capital is being aligned with risk, as per the new Transfer Payment Policy (to be aligned with item 1.a.)

b) Operations and Planning Support Branch to implement in regions comprehensive national guidelines for the categorization of projects to be managed as major capital projects. 30/09/2009 b) Ongoing - The Management Control Framework has been implemented in cooperation with OPSB. Work is ongoing to align program risk for Major Capital projects with the General Assessment tool to measure recipient risk currently being developed and tested in regions by Regional Operations Branch and with program risk tools being developed by INAC's Audit and Evaluation Sector.

AES: Close

6 b) The Director General, Operations and Planning Support Branch should establish processes for the ongoing monitoring of regional practices by Headquarters. Operations and Planning Support Branch to establish processes for the ongoing monitoring of major capital regional practices (i.e., file review, project approval process) by Headquarters, including communication interface between Operations and Planning Support Branch and Community Infrastructure Branch. 30/09/2009 Status: Completed

Update/Rationale:
As of 31/03/2010:

6. b) Completed - CFM Program Management Control Framework establishes processes for ongoing monitoring of regional practices by HQ. HQ is responsible for conducting annual major capital project file reviews to ensure that regions have undertaken major capital projects according to established guidelines. A Project Brief Review committee has also been established to examine major capital projects as presented to HQ. The committee reviews and makes recommendations on the proposed Project Brief to Directors General in preparation for consideration by Operations Committee. OPSB also annually reviews a sample of all major capital projects completed during the previous year according to procedures outlined in the Management Control Framework. File reviews focus on how well the region met the guidelines for file requirements for a specific project. Where file reviews reveal deficiencies, HQ will recommend remedial action to improve compliance with guidelines.

AES: Close

7 a) The Director General, Community Infrastructure Branch should ensure that national comprehensive guidelines for management of the CFM Program (as recommended in item #5.1) include major capital project file documentation requirements to address key risk areas. a) Community Infrastructure Branch to draft/update comprehensive national guidelines for major capital project file documentation requirements to address key risk areas. 30/09/2009 Status: Completed

Update/Rationale:
As of 31/03/2010:

7a. Completed - CFM Management Control Framework has been developed and approved by Operations Committee. A Major Capital document checklist has been drafted and included as an appendix to the Management Control Framework.

b) Operations and Planning Support Branch to implement in regions comprehensive national guidelines for the management of the CFM Program that include major capital project file documentation requirements, which address key risk areas. 30/09/2009 b. Completed - OPSB has implemented the CFM Management Control Framework in the regions and has conduced file reviews in regions of high risk projects, including a sample of CEAP projects and of all major capital projects valued over $10 million.

AES: Close

7 b) The Director General, Operations and Planning Support Branch should establish processes for the ongoing monitoring of regional practices by Headquarters to assess compliance with the guidelines. Operations and Planning Support Branch to establish processes for the ongoing monitoring of regional practices by Headquarters to assess compliance with guidelines as they relate the major capital project file documentation. 31/12/2009 Status: Completed

Update/Rationale:
As of 31/03/2010:

7. b) Completed - OPSB also annually reviews a sample of all major capital projects completed during the previous year according to procedures outlined in the Management Control Framework. File reviews focus on how well the region met the guidelines for file requirements for a specific project. Where file reviews reveal deficiencies, HQ will recommend remedial action to improve compliance with guidelines.

AES: Close

8 a) The Director General, Community Infrastructure Branch should develop guidelines outlining minimum requirements or expectations, including monitoring, for the management and oversight of minor capital and operations & maintenance. a) Community Infrastructure Branch to draft/update guidelines detailing minimum requirements for the management of oversight of minor capital and operations & maintenance. 31/09/2009 Status: Pending Implementation

Update/Rationale:
As of 31/03/2010:

8. a) Ongoing - Preliminary recommendations for establishing guidelines for minor capital have been drafted based on reviews of documents and practices provided by regions. A minor capital working group is being established in cooperation with OPSB and regions to develop strengthened procedures for managing minor capital funding. Work is ongoing to develop procedures for Operations and Maintenance funding. Regional Operations and Maintenance compliance activities for fiscal year 2010-2011 are being analysed to inform the development of national procedures for Operations and Maintenance compliance and management.

AES: No comment at this time.

b) Operations and Planning Support Branch to implement in regions guidelines detailing minimum requirements for the management of oversight of minor capital and operations & maintenance. 31/03/2010
8 b) The Director General, Operations and Planning Support Branch should work closely with the Chief Financial Officer to establish processes for the ongoing monitoring of regional practices by Headquarters to assess compliance with the guidelines. Operations and Planning Support Branch to work with Chief Financial Office to establish processes for the ongoing monitoring of regional practices by Headquarters to assess compliance with the minor capital and operations & maintenance guidelines. 31/03/2010 Status: On completion of above (a)

Update/Rationale:
As of 31/03/2010:

b. OPSB will implement guidelines detailing requirements for management and oversight of minor capital and operations and maintenance.

AES: No comment at this time

9. The Director General, Community Infrastructure Branch and the Director General , Operations and Planning Support Branch should consider the implementation of risk based FN compliance audits as part of a formalized risk management framework. a) Community Infrastructure Branch to work with Operations and Planning Support Branch to develop compliance audit framework and process for the CFM Program, building upon the compliance audit work that has been undertaken specifically for the First Nations Water and Wastewater Action Plan. 31/12/2009 Status: Pending Implementation

Update/Rationale:
As of 31/03/2010:

9) a. Ongoing - this is being developed simultaneously with the development of CFM Program procedures outlined in item 5 above to align compliance regimes with overall program delivery. A Risk Profile has been created and implemented for the CFM Program and was approved by the Department's Evaluation, Performance Measurement and Review Branch in September 2009. Risk-based approaches for program management are being considered and developed in coordination with the General Assessment tool to assess recipient risk that is being developed by Regional Operations.

b) Operations and Planning Support Branch, with support from Community Infrastructure Branch, to implement the compliance audit framework and processes in the regions. 31/03/2010 b. Pending implementation following completion of part (a)

AES: No comment at this time. Past expected completion date.

 
 

Did you find what you were looking for?

What was wrong?

You will not receive a reply. Don't include personal information (telephone, email, SIN, financial, medical, or work details).
Maximum 300 characters

Thank you for your feedback

Date modified: