This Web page has been archived on the Web. Archived information is provided for reference, research or record keeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.

PDF Version (24 Kb, 1 Page)

 

 

Action Plan Implementation Status Update
Report To The Audit Committee - As Of September 30, 2009

Resolution and Individual Affairs Sector-Dispute Resolution Operation

Financial Audit of the Settlement Allotment (200818)
AEC Approval Date: 22/04/2009

Project Recommentations Action Plan Expected Completion Date Program Response
1. The General Director of the Dispute Resolution Operations Branch should leverage the existing tracking database to ensure that all claims and original supporting documentation are accounted for, throughout the life cycle of the claim. The database is now used to ensure that all claims and original supporting documentation is accounted for once a decision has been made by an adjudicator or a settlement has been reached with the claimant. April 1, 2009 Update/Rationale: As of 30/09/2009:

Changes were implemented in SADRE on September 25, 2009 to include the compensation process flow. Further changes are required to fully integrate the compensation process in the SADRE database. These changes have been submitted to IT and are scheduled to be released in production on November 27, 2009. A transition plan is being developed to ensure that the benefits of this integration are fully realized.

AES: Expect to close in March 2010.
 
 

Did you find what you were looking for?

What was wrong?

You will not receive a reply. Don't include personal information (telephone, email, SIN, financial, medical, or work details).
Maximum 300 characters

Thank you for your feedback

Date modified: